Authority Updates


Please be advised - beginning Monday, September 30th  2024 -

we will be initiating our biannual, system-wide flushing program.


Any neighborhood falling within the highlighted Yellow Zones below are scheduled for flushing on the date provided above. 

If you are unsure as to whether your address falls within or near these zones, please follow the following steps:

1. Select the "View Larger Map" button in the top, right corner of the map window.
2. Once the map has opened in a new tab, click the magnifying glass to the right of the map title.
3. Type your house address in the search bar, and hit the "Enter" key.





                                                                                                                           


PLEASE CLICK HERE FOR MORE INFORMATION REGARDING ACTIVE PROJECTS

2024 INFRASTRUCTURE REPLACEMENT & CONSTRUCTION WORK

Kent County Water Authority is performing water main replacement and installation as well as pavement restoration work in the areas listed below during the 2024 construction season.  This work may disrupt normal traffic.  If you are a customer who frequently drives in these areas, it is strongly recommended that traffic-related delays be factored into your travel plans.

Additional information and mapping for each construction area is provided below.


West Warwick - Cowesett Avenue

The Infrastructure Replacement Program IFR 2022 construction bid was awarded on October 27, 2022 and work started on April 17th,2023. IFR 2022 was designed to continue the aggressive replacement of critical infrastructure for several high priority locations within the KCWA distribution system. This project generally involves the installation of water mains in the Town of West Warwick. This project is essential in providing enhanced water quality, increased pressure, fire protection, and resiliency for 100,000 people in the eight cities and towns we service. This project encompasses installing pipelines consisting of approximately 7,600 linear feet of 16-inch ductile iron pipe, 4,360 linear feet of 12-inch ductile iron pipe and 2,100 linear feet of 8-inch ductile iron pipe. Specifically, the project involves the replacement of 1887 vintage cast iron main along Cowesett Avenue and Main Street. While under the roadway, KCWA is simultaneously installing a separate high service line to loop several dead-end mains and reservice localized areas of historic low pressures in and around Carlson Circle.  A major component to this project, and the most critical, is the replacement and relocation of the water main at the intersection of Cowesett Avenue and Quaker Lane where there was gas infrastructure that was built on top of the water main.   


Construction Schedule -  (UPDATED October 4, 2024)


Phase II Water Main Installation Complete 12" & 16"

October 1, 2024 - October 25, 2024 - Installation of services and tie-ins - Coit Ave. to Quaker Ln. (Alternating Traffic) (Various Locations) (Status: In Progress)

October 7, 2024 - October 15, 2024 - Testing 8" water main - Fairgreen Dr. (Status: Not Yet Started)

October 7, 2024 to November 8, 2024 - Final paving curb to curb - Milling and Overlay -  New London Turnpike to Coit Ave. on Main St. and Cowesett Ave. (Alternating Traffic) (Status: In Progress)


Map - Cowesett Avenue Water Main Replacement and Installation


Warwick - Bald Hill Road and Toll Gate Road

October 6, 2024 - October 25, 2024 -  Permanent pavement restoration will take place Sunday through Thursday Nights 9PM-5AM. (Alternating Traffic) (Status: In Progress) 

Map - Bald Hill Road and Toll Gate Road Water Main Installation and Replacement










A Note to our Valued Customers:


  Contact Information

Hours: Mon-Fri, 8am to 4pm
  Phone: (401) 821-9300
  Fax: (401) 823-4810
  Email Customer Service

35 Technology Way
West Greenwich, RI 02817
  Directions